Lifetime Fitness

LIFETIME PARKING GARAGE AND FACILITY

Palm Beach Gardens, FL

Dewater for construction of the facility foundation and the parking garage.

THE CHALLENGE

Part of the main building foundation had been excavated prior to installing a dewatering system and the site was not level in areas. In addition, we had to work around the existing utilities. We were able to install the system with track punch method and dewater the main foundation. We remobilized 6 months later to install a perimeter dewatering system for the parking garage foundation. We again had to work around existing utilities and needed to keep a large gap in the system for trucks to enter and exit.

THE SOLUTION

We installed approximately 1,000 LF of wellpoint system around the perimeter of the main facility and approximately 900 LF of wellpoint system around the perimeter of the parking garage. We closed the spacing on the parking garage wellpoints to ensure we completed drawn down for the deep excavations near the large opening within the system.

GRIFFIN DIFFERENCE

The project was successfully completed on-time in two phases to accommodate the construction schedule. The high water table, tight working conditions and logistical challenges were overcome by Griffin’s expert engineering and operations teams.

READY FOR YOUR PROJECT?